72 FR 139 pgs. 39892-39893 - Office of Hazardous Materials Safety; Notice of Delays in Processing of Special Permits Applications
Type: NOTICEVolume: 72Number: 139Pages: 39892 - 39893
FR document: [FR Doc. 07-3543 Filed 7-19-07; 8:45 am]
Agency: Transportation Department
Sub Agency: Pipeline and Hazardous Materials Safety Administration
Official PDF Version: PDF Version
DEPARTMENT OF TRANSPORTATION
Pipeline and Hazardous Materials Safety Administration
Office of Hazardous Materials Safety; Notice of Delays in Processing of Special Permits Applications
AGENCY:
Pipeline and Hazardous Materials Safety Administration (PHMSA), DOT.
ACTION:
List of applications delayed more than 180 days.
SUMMARY:
In accordance with the requirements of 49 U.S.C. 5117(c), PHMSA is publishing the following list of special permit applications that have been in process for 180 days or more. The reason(s) for delay and the expected completion date for action on each application is provided in association with each identified application.
FOR FURTHER INFORMATION CONTACT:
Delmer F. Billings, Director, Office of Hazardous Materials Special Permits and Approvals, Pipeline and Hazardous Materials Safety Administration, U.S. Department of Transportation, East Building, PHH-30, 1200 New Jersey Avenue, Southeast, Washington, DC 20590-0001, (202) 366-4535.
Key to "Reason for Delay"
1. Awaiting additional information from applicant.
2. Extensive public comment under review.
3. Application is technically complex and is of significant impact or precedent-setting and requires extensive analysis.
4. Staff review delayed by other priority issues or volume of special permit applications.
Meaning of Application Number Suffixes
N-New application.
M-Modification request.
PM-Party to application with modification request.
Issued in Washington, DC, on July 16, 2007.
Delmer F. Billings,
Director, Office of Hazardous Materials, Special Permits and Approvals.
Application number | Applicant | Reason for delay | Estimated date of completion |
---|---|---|---|
10481-M | M-1 Engineering Limited Bradfrod, West Yorkshire | 4 | 09-30-2007 |
114167-M | Trinityrail Dallas, TX | 1,3,4 | 09-30-2007 |
Application number | Applicant | Reason for delay | Estimated date of completion |
---|---|---|---|
14385-N | Kansas City Southern Railway Company Kansas City, MO | 4 | 09-30-2007 |
14442-N | Trinityrail Dallas, TX | 4 | 09-30-2007 |
14468-N | REC Advanced Silicon Materials LLC Butte, MT | 4 | 09-30-2007 |
14470-N | Marsulex, Inc. Springfield, OR | 4 | 08-31-2007 |
14469-N | Space Systems/Loral Palo Alto, CA | 4 | 07-31-2007 |
14457-N | Ambrol Alfa Metalomecanica SA Portugal | 4 | 09-30-2007 |
14436-N | BNSF Railway Company Topeka, KS | 4 | 09-30-2007 |
14402-N | Lincoln Composites Lincoln, NE | 1 | 12-31-2007 |
[FR Doc. 07-3543 Filed 7-19-07; 8:45 am]